2022-06-14 Beiqing.com
The newspaper (Correspondent Dong Chenguang reporter Wu Zhongxiang) Recently, the first component of the second phase of the 6GW high -power solar photovoltaic component project in Jingshan Factory District, Yangzhou Jingao Company was officially launched. It is reported that after the second -phase component of the 6GW phase is full, Yangzhou Jing'ao will form a 10GW component production scale, and the annual output value can reach 18 billion to 19 billion yuan. The formal investment in the project also marks that Yangzhou Jing'ao has become the largest component production base in Jing'ao Group.
"6GW component second phase of the project uses 40,000 square meters of the plant, a total of 8 production lines, and 4GW component production capacity can be formed after delivery. 500 new jobs can be added. The annual output value is about 8 billion yuan. Growing point. "Ge Quan, director of the New Energy Industry Office of Yangzhou Economic Development Zone.
In December 8 last year, the first phase of the 6GW component project in Yangzhou Jing'ao and the first phase of the 6GW battery were officially put into operation at the same time, with a total investment of 10 billion yuan. The 6GW component project construction 6GW high -performance component production line, the factory area covers an area of about 385 acres. After the project is fully put into production, it has 14 component production lines. It has formed an industrial support with Jinghui Factory District.
The Yangzhou Jing'ao takes the project to advance the project as the "headline" of the company. At the entrepreneur development conference held by Yangzhou Economic Development Zone on May 26 this year, Guo Yafei, general manager of Yangzhou Jing'ao, said that the total investment of 10 billion yuan in Yangzhou Jing'ao's total investment was officially implemented, marking that Yangzhou Jing'ao Company has achieved a major leap -up type develop. Among them, the "6GW battery project" was put into production in October 2021, and has been fully produced as of now; 6 production lines in the "6GW component project" in October 2021 were put into production in October 2021. The second phase of 8 production lines have been installed and commissioned in May this year. At the speed of adding 1 new production line debugging per week, it is expected that all 8 production line debugging work will be completed by the end of June.
The Yangzhou Jing'ao side installation and commissioning is prepared. Recently, the first component of Yangzhou Jingao Component 6GW component project was officially offline. "After the project is fully produced, Yangzhou Jing'ao will also fully form a vertical integration layout of the" double 10GW 'battery and component's industrial chain. The company's scale will be further expanded, which will continue to contribute to the power of Jing'ao for the "secondary flight" of the Economic Development Zone. " Guo Yafei said.
It is reported that the second phase of the 6GW component project was planned to start in early May this year. In view of the situation of the prevention and control of the epidemic, the Yangzhou Economic Development Zone New Energy Industrial Park and the relevant departments of Bali Town and relevant departments of the Yangzhou Economic Development Zone set up a work class. Former service, tailor -made personnel, equipment and logistics special epidemic prevention guidance schemes for Yangzhou Jing'ao. "In the case of insisting on dynamic zero -epidemic prevention chess, the industrial park has done its best to ensure the debugging operation of the project and assist enterprises to seize development opportunities. Eight production lines completed the installation in just 21 days." Ge Quan introduced.
(Yangzhou Daily)
2022-06-14 北青网
本报讯(通讯员 董晨光 记者 吴忠祥) 近日,扬州晶澳公司晶山厂区6GW高功率太阳能光伏组件二期项目首块组件正式下线,满产后可增加年产值近80亿元。据悉,待6GW二期组件满产后,扬州晶澳将形成10GW组件生产规模,年产值可达到180亿—190亿元。该项目正式投产,也标志着扬州晶澳成为晶澳集团最大的组件生产基地。
“6GW组件二期项目使用厂房40000平方米,共8条生产线,待满产后可形成4GW组件产能,新增500个就业岗位,年产值约80亿元,成为晶澳集团布局扬州的重要增长点。”扬州经开区新能源产业办公室主任葛权介绍。
去年12月8日,扬州晶澳6GW组件一期项目与6GW电池一期项目同时正式投产,总投资100亿元。6GW组件项目建设6GW高性能组件生产线,厂区占地面积约385亩,项目全面投产后拥有组件生产线14条,与晶辉厂区形成电池项目形成产业配套,继续领军扬州光伏行业发展。
扬州晶澳把项目推进速度作为公司“头版头条”。在今年5月26日扬州经开区举办的企业家发展大会上,扬州晶澳总经理郭亚菲表示,扬州晶澳总投资100亿元项目正式实施,标志着扬州晶澳公司实现了重大的跨越式发展。其中“6GW电池项目”于2021年10月投产,截至目前已经全面达产;“6GW组件项目”一期6条生产线于2021年10月投产,二期8条生产线已于今年5月安装调试,以每周新增1条产线调试的速度推进,预计6月底完成全部8条产线调试工作。
扬州晶澳边安装调试边试生产,日前,扬州晶澳公司6GW组件二期项目首块组件正式下线。“项目完全达产后,扬州晶澳也将全面形成‘双10GW’电池加组件的产业链垂直一体化布局,企业规模进一步扩大,为经开区的‘二次腾飞’继续贡献晶澳力量。”郭亚菲表示。
据悉,6GW组件二期项目于今年5月初筹划启动,鉴于疫情防控形势,扬州经开区新能源产业园联合晶澳公司所在的八里镇及相关部门成立工作专班,主动作为、靠前服务,为扬州晶澳量身定制人员、设备和物流等专项防疫指导方案。“在坚持动态清零防疫一盘棋的情况下,产业园尽最大努力保障该项目调试运行,协助企业抢抓发展机遇,8条生产线仅用21天就完成了安装。”葛权介绍。
(扬州日报)